United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2017 requests) โ€” page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,258161.7 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,258 requests ยท page 23 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AC2-131, Chesterfield County
Gas
14.3 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2017target 2017
Clare Rose
Battery storage ยท CR Fuel Cell, LLC
13.9 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2017
Solar project 887, Jackson County
Solar
13.0 MWWithdrawn / abandoned Jackson, ORWest May 2017target 2018
Hollyfield II
Solar
13.0 MWWithdrawn / abandoned King William, VAPJM Feb 2017target 2021
Solar project 55, Nez Perce County
Solar
12.5 MWWithdrawn / abandoned Nez Perce, IDWest May 2017target 2018
Cherry Valley Solar Project, LLC
Solar
12.5 MWWithdrawn / abandoned Boone, ILPJM Sep 2017target 2026
Gas project AC2-180, Campbell County
Gas
12.0 MWWithdrawn / abandoned Campbell, VAPJM Mar 2017target 2018
Solar project AD1-159, City Of Chesapeake County
Solar
12.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2017target 2019
Other project AC2-189, Somerset County
Other
11.6 MWWithdrawn / abandoned Somerset, MDPJM Mar 2017target 2018
Westwood Rd
Solar ยท Solar Liberty Energy Systems, Inc.
11.3 MWWithdrawn / abandoned Erie, NYNYISO Sep 2017
Oak Grove III
Solar
11.2 MWWithdrawn / abandoned Westmoreland, VAPJM Jul 2017target 2021
Gas project AC2-132, Chesterfield County
Gas
11.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2017target 2017
Solar project AD1-040, Albemarle County
Solar
11.0 MWWithdrawn / abandoned Albemarle, VAPJM Jul 2017target 2018
Main St
Solar ยท Solar Liberty Energy Systems, Inc.
10.8 MWWithdrawn / abandoned NYNYISO Sep 2017
Gas project GI-2017-15, Weld County
Gas
10.6 MWWithdrawn / abandoned Weld, COWest May 2017target 2019
Solar project AD1-146, Sussex County
Solar
10.0 MWWithdrawn / abandoned Sussex, DEPJM Sep 2017target 2019
Solar project AC2-051, Pickaway County
Solar
10.0 MWWithdrawn / abandoned Pickaway, OHPJM Feb 2017target 2018
Solar project AC2-019, Highland County
Solar
10.0 MWWithdrawn / abandoned Highland, OHPJM Jan 2017target 2019
Solar project 990, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Dec 2017target 2019
Solar project AC2-054, Muskingum County
Solar
10.0 MWWithdrawn / abandoned Muskingum, OHPJM Feb 2017target 2018
Solar project AC2-153, Dekalb County
Solar
10.0 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2017target 2019
Solar project 880, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest May 2017target 2018
Solar project AD1-123, Halifax County
Solar
10.0 MWWithdrawn / abandoned Halifax, VAPJM Sep 2017target 2018
Maverick
Battery storage
10.0 MWWithdrawn / abandoned San Diego, CACAISO May 2017target 2021
Vernon Battery Storage II
Battery storage ยท Helix Ravenswood, LLC
10.0 MWWithdrawn / abandoned Queens, NYNYISO Oct 2017
Solar project 957, Klamath County
Solar
10.0 MWWithdrawn / abandoned Klamath, ORWest Oct 2017target 2019
Solar project 989, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Dec 2017target 2019
Solar Power and Light, LLC
Solar
10.0 MWWithdrawn / abandoned Athens, OHPJM Feb 2017target 2019
Solar project AC2-152, Livingston County
Solar
10.0 MWWithdrawn / abandoned Livingston, ILPJM Mar 2017target 2019
Vernon Battery Storage I
Battery storage ยท Helix Ravenswood, LLC
10.0 MWWithdrawn / abandoned Queens, NYNYISO Oct 2017
Solar project AC2-028, Highland County
Solar
10.0 MWWithdrawn / abandoned Highland, OHPJM Jan 2017target 2018
Solar project SGI-PNM-2017-07, Santa Fe County
Solar
10.0 MWWithdrawn / abandoned Santa Fe, NMWest Jun 2017target 2018
Solar project 870, Umatilla County
Solar
10.0 MWWithdrawn / abandoned Umatilla, ORWest May 2017target 2019
Solar project AC2-095, Clermont County
Solar
10.0 MWWithdrawn / abandoned Clermont, OHPJM Mar 2017target 2019
Seneca Energy
Solar
10.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2017target 2025
Solar project SGI-PNM-2017-01, Luna County
Solar
10.0 MWWithdrawn / abandoned Luna, NMWest Jan 2017target 2018
Solar project LGE-GIS-2017-005, Harrison County
Solar
10.0 MWWithdrawn / abandoned Harrison, KYSoutheast Aug 2017target 2018
Onshore wind project GEN-2017-241, Dawson County
Onshore wind
10.0 MWWithdrawn / abandoned Dawson, NESPP Jul 2017target 2018
Columbia County 3
Solar ยท Hecate Energy Craryville 3, LLC
10.0 MWWithdrawn / abandoned Columbia, NYNYISO Feb 2017
Solar project AC2-193, Camden County
Solar
10.0 MWWithdrawn / abandoned Camden, NJPJM Mar 2017target 2017
Solar project 869, Sherman County
Solar
10.0 MWWithdrawn / abandoned Sherman, ORWest May 2017target 2019
Solar project AC2-027, Highland County
Solar
10.0 MWWithdrawn / abandoned Highland, OHPJM Jan 2017target 2018
Solar project 847, Sweetwater County
Solar
10.0 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2017target 2018
Solar project AD1-027, Camden County
Solar
10.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2017target 2017
Double Tollgate Solar Project
Solar
10.0 MWWithdrawn / abandoned Clarke, VAPJM Apr 2017target 2023
Rosebud
Battery storage
10.0 MWWithdrawn / abandoned San Diego, CACAISO May 2017target 2021
Other project AD1-145, Sussex County
Other
9.6 MWWithdrawn / abandoned Sussex, DEPJM Sep 2017target 2019
Other project AC2-191, Sussex County
Other
9.6 MWWithdrawn / abandoned Sussex, DEPJM Mar 2017target 2018
Other project AC2-190, Sussex County
Other
9.6 MWWithdrawn / abandoned Sussex, DEPJM Mar 2017target 2018
Solar project AC2-134, Sussex County
Solar
9.0 MWWithdrawn / abandoned Sussex, NJPJM Mar 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)