United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in the USA (2023 requests) β€” page 22

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,065262.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,065 requests Β· page 22 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AI2-467, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-469, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-459, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-470, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-477, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AI2-312, Venango County
Solar
5.5 MWIn study Venango, PAPJM Mar 2023target 2022
Solar project AI2-043, Northumberland County
Solar
5.0 MWIn study Northumberland, VAPJM Jan 2023target 2024
Solar Increase
Solar
5.0 MWIn study Hartford, CTISO-NE Feb 2023target 2027
Solar + storage project 440, Lewis And Clark County
Solar + storage
4.6 MWIn study Lewis And Clark, MTWest Jan 2023target 2023
Solar project AI2-308, Bedford County
Solar
4.4 MWIn study Bedford, PAPJM Mar 2023target 2024
Solar project C3-148, Crook County
Solar Β· CP Prineville, LLC
3.0 MWIn study Crook, ORWest May 2023target 2033
Solar project G1003, Adams County
Solar
3.0 MWIn study Adams, WAWest Nov 2023target 2025
Solar project 454, Gallatin County
Solar
2.0 MWIn study Gallatin, MTWest Dec 2023target 2024
Solar project G0943, Snohomish County
Solar
1.0 MWIn study Snohomish, WAWest Oct 2023target 2024
Solar project G0968, Clark County
Solar
1.0 MWIn study Clark, WAWest Oct 2023target 2023
Page 22 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)