United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 22

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 22 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-560, Will County
Battery storage · University Park Energy, LLC
150 MWWithdrawn / abandoned Will, ILPJM Sep 2021target 2025
Battery storage project AG1-069, Warren County
Battery storage
150 MWWithdrawn / abandoned Warren, VAPJM Jul 2020target 2023
Onshore wind project AD1-064, Dekalb County
Onshore wind
150 MWWithdrawn / abandoned Dekalb, ILPJM Aug 2017target 2019
Onshore wind project W3-022, Schuylkill County
Onshore wind
150 MWWithdrawn / abandoned Schuylkill, PAPJM Aug 2010target 2016
Onshore wind project P21, Bureau County
Onshore wind
150 MWWithdrawn / abandoned Bureau, ILPJM Oct 2005target 2007
Solar project AB2-131, Marion County
Solar
150 MWWithdrawn / abandoned Marion, OHPJM Apr 2016target 2019
Solar + storage project AG2-034, Greensville County
Solar + storage
150 MWWithdrawn / abandoned Greensville, VAPJM Nov 2020target 2024
Solar project AG2-681, Perry County
Solar
150 MWWithdrawn / abandoned Perry, KYPJM Mar 2021target 2024
Solar project AF2-063, Louisa County
Solar · AURA POWER DEVELOPMENTS (USA), LLC
150 MWWithdrawn / abandoned Louisa, VAPJM Jan 2020target 2023
Stark Solar
Solar
150 MWWithdrawn / abandoned Stark, OHPJM Sep 2020target 2028
Onshore wind project S118, Paulding County
Onshore wind
150 MWWithdrawn / abandoned Paulding, OHPJM Jul 2007target 2008
Battery storage project AG2-322, James City County
Battery storage
150 MWWithdrawn / abandoned James City, VAPJM Mar 2021target 2023
Solar project AH1-599, Lee County
Solar
150 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Onshore wind project AD2-143, Randolph County
Onshore wind
150 MWWithdrawn / abandoned Randolph, INPJM Mar 2018target 2020
Onshore wind project H04_W64, Grant County
Onshore wind
150 MWWithdrawn / abandoned Grant, WVPJM Sep 2001target 2005
Battery storage project AG2-287, Loudoun County
Battery storage
150 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Battery storage project AG2-320, Caroline County
Battery storage · Ladysmith Storage, LLC
150 MWWithdrawn / abandoned Caroline, VAPJM Feb 2025target 2023
Battery storage project AH1-453, Vermillion County
Battery storage
150 MWWithdrawn / abandoned Vermillion, INPJM Sep 2021target 2028
Battery storage project AH1-751, Green County
Battery storage · Exie Solar, LLC
150 MWWithdrawn / abandoned Green, KYPJM target 2029
Onshore wind project AD2-141, Will County
Onshore wind
150 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Solar project AG2-619, Queen Anne's County
Solar
150 MWWithdrawn / abandoned Queen Anne's, MDPJM Mar 2021target 2023
Mt Storm WF
Onshore wind
150 MWWithdrawn / abandoned Grant, WVPJM Jul 2004target 2015
Battery storage project AH1-604, Crawford County
Battery storage
150 MWWithdrawn / abandoned Crawford, OHPJM Sep 2021target 2025
Onshore wind project AG1-435, Bureau County
Onshore wind · RWE Clean Energy Development, LLC
150 MWWithdrawn / abandoned Bureau, ILPJM Sep 2020target 2023
Solar project AH1-400, Madison County
Solar
150 MWWithdrawn / abandoned Madison, INPJM Sep 2021target 2025
Battery storage project AG2-302, Montgomery County
Battery storage
150 MWWithdrawn / abandoned Montgomery, MDPJM Mar 2021target 2023
Onshore wind project AD2-152, Wayne County
Onshore wind
150 MWWithdrawn / abandoned Wayne, PAPJM Mar 2018target 2020
Battery storage project AH1-616, Cook County
Battery storage
150 MWWithdrawn / abandoned Cook, ILPJM Sep 2021target 2025
Solar project AE1-242, Christian County
Solar
150 MWWithdrawn / abandoned Christian, ILPJM Sep 2018target 2022
Solar project AF1-156, Kankakee County
Solar
150 MWWithdrawn / abandoned Kankakee, ILPJM Sep 2019target 2021
Battery storage project AG2-309, New Kent County
Battery storage
150 MWWithdrawn / abandoned New Kent, VAPJM Mar 2021target 2023
Solar project AG1-220, Dekalb County
Solar
150 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2020target 2023
Onshore wind project AA2-039, Henry County
Onshore wind
150 MWWithdrawn / abandoned Henry, ILPJM Jan 2015target 2016
Solar project AE1-252, Livingston County
Solar
150 MWWithdrawn / abandoned Livingston, ILPJM Sep 2018target 2021
Battery storage project AG2-304, Prince William County
Battery storage · Urban Grid Solar Projects, LLC
150 MWWithdrawn / abandoned Prince William, VAPJM Jan 2025target 2023
Solar + storage project AF1-279, Lorain County
Solar + storage
150 MWWithdrawn / abandoned Lorain, OHPJM Sep 2019target 2022
Solar project AE2-050, Will County
Solar
150 MWWithdrawn / abandoned Will, ILPJM Jan 2019target 2021
Battery storage project AG1-020, Loudoun County
Battery storage
150 MWWithdrawn / abandoned Loudoun, VAPJM May 2020target 2023
Battery storage project AG2-285, Loudoun County
Battery storage
150 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Solar project AF2-216, Union County
Solar
150 MWWithdrawn / abandoned Union, OHPJM Mar 2020target 2024
Solar project AH1-437, Culpeper County
Solar
150 MWWithdrawn / abandoned Culpeper, VAPJM Sep 2021target 2026
Onshore wind project AD2-150, Dekalb County
Onshore wind
150 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2018target 2020
Solar project AG1-075, Greensville County
Solar · Jarratt Solar, LLC
150 MWWithdrawn / abandoned Greensville, VAPJM Jul 2020target 2024
Battery storage project AH1-579, Union County
Battery storage
150 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2028
Onshore wind project AD2-137, Will County
Onshore wind
150 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Battery storage project AG2-319, Anne Arundel County
Battery storage
150 MWWithdrawn / abandoned Anne Arundel, MDPJM Mar 2021target 2025
Solar project AG2-580, Brunswick County
Solar · Bellflower Holdings, LLC
150 MWWithdrawn / abandoned Brunswick, VAPJM Jan 2021target 2024
Battery storage project AG2-306, Prince William County
Battery storage
150 MWWithdrawn / abandoned Prince William, VAPJM Mar 2021target 2023
Beech Hollow
Gas
150 MWWithdrawn / abandoned Washington, PAPJM Jul 2004target 2015
Battery storage project AG2-113, Prince William County
Battery storage
150 MWWithdrawn / abandoned Prince William, VAPJM Jan 2021target 2022
Page 22 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)