Queue requests in study in Utah — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12929.7 GW
Active in queue33.8 GW154 requests
Agreement signed4,095 MW25 requests
Withdrawn64684.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

129 requests · page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project C2-02, Juab County
Gas · PacifiCorp
200 MWIn study Juab, UTWest Apr 2022target 2026
Battery storage project PIS088, Salt Lake County
Battery storage
199 MWIn study Salt Lake, UTWest Sep 2024target 2028
Solar + storage project C2-57, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Battery storage project C2-109, Utah County
Battery storage
199 MWIn study Utah, UTWest May 2022target 2025
Solar + storage project T2-062, Utah County
Solar + storage
199 MWIn study Utah, UTWest Sep 2025target 2027
Solar + storage project C3-132, Millard County
Solar + storage
199 MWIn study Millard, UTWest May 2023target 2027
Battery storage project C2-110, Utah County
Battery storage
199 MWIn study Utah, UTWest May 2022target 2025
Solar + storage project C2-131, Emery County
Solar + storage
199 MWIn study Emery, UTWest May 2022target 2026
Solar + storage project C2-115, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project C2-59, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar project PIS043, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar + storage project C2-56, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar project PIS042, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar + storage project C2-58, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project T2-060, Utah County
Solar + storage
199 MWIn study Utah, UTWest Sep 2025target 2027
Solar + storage project C2-112, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2025
Solar + storage project 785, Juab County
Solar + storage
199 MWIn study Juab, UTWest Apr 2025target 2027
Solar + storage project T2-071, San Juan County
Solar + storage
199 MWIn study San Juan, UTWest Sep 2025target 2028
Solar + storage project C1-16, Millard County
Solar + storage · Neptune Solar Energy Park LLC
199 MWPaused / redesign Millard, UTWest May 2021target 2025
Solar + storage project PIS105, Emery County
Solar + storage
199 MWIn study Emery, UTWest Dec 2025target 2026
Solar + storage project C1-54, Utah County
Solar + storage · Pinyon Creek Solar LLC
199 MWPaused / redesign Utah, UTWest May 2021target 2024
Battery storage project PIS026, Utah County
Battery storage
199 MWIn study Utah, UTWest Jul 2022target 2025
Battery storage project PIS025, Utah County
Battery storage
199 MWIn study Utah, UTWest Jul 2022target 2025
Solar + storage project T2-063, Utah County
Solar + storage
199 MWIn study Utah, UTWest Sep 2025target 2027
Gas project T2-035, Millard County
Gas
185 MWIn study Millard, UTWest Sep 2025target 2029
Solar project PIS056, Emery County
Solar · PacifiCorp
178 MWIn study Emery, UTWest May 2024target 2026
Solar + storage project T2-055, Juab County
Solar + storage
175 MWIn study Juab, UTWest Sep 2025target 2029
Solar + storage project C2-99, Emery County
Solar + storage
166 MWIn study Emery, UTWest May 2022target 2026
Battery storage project T2-080, Salt Lake County
Battery storage
160 MWIn study Salt Lake, UTWest Sep 2025target 2027
Solar + storage project T2-037, Emery County
Solar + storage
150 MWIn study Emery, UTWest Sep 2025target 2028
Solar project PIS027, Utah County
Solar
150 MWIn study Utah, UTWest Jul 2022target 2025
Solar project PIS057, Emery County
Solar · PacifiCorp
125 MWIn study Emery, UTWest May 2024target 2026
Solar project C2-167, Emery County
Solar · PacifiCorp
125 MWIn study Emery, UTWest May 2022target 2026
Battery storage project S0033, Washington County
Battery storage
122 MWIn study Washington, UTWest Dec 2024target 2027
Solar + storage project C1-14, Emery County
Solar + storage · Muddy Creek Energy, LLC
120 MWPaused / redesign Emery, UTWest Apr 2021target 2029
Battery storage project S0036, Emery County
Battery storage
100 MWIn study Emery, UTWest Jun 2025target 2027
Solar + storage project T2-054, Utah County
Solar + storage
100 MWIn study Utah, UTWest Sep 2025target 2027
Solar project C2-169, Tooele County
Solar · PacifiCorp
99.0 MWPaused / redesign Tooele, UTWest May 2022target 2026
Onshore wind project BPA, Box Elder County
Onshore wind
95.0 MWIn study Box Elder, UTWest Aug 2009
Solar project 805, Kane County
Solar · Glen Canyon Solar A, LLC
95.0 MWIn study Kane, UTWest Sep 2016target 2019
Solar project S0020, Tooele County
Solar
80.0 MWIn study Tooele, UTWest Dec 2022target 2026
Battery storage project S0031, Box Elder County
Battery storage
80.0 MWIn study Box Elder, UTWest Aug 2024target 2026
Battery storage project S0034, Juab County
Battery storage
80.0 MWIn study Juab, UTWest Dec 2024target 2026
Battery storage project S0018, Tooele County
Battery storage
75.0 MWIn study Tooele, UTWest Dec 2022target 2026
Solar + storage project PIS106, Miller County
Solar + storage
75.0 MWIn study Miller, UTWest Dec 2025target 2027
Solar + storage project C3-125, Millard County
Solar + storage
75.0 MWIn study Millard, UTWest May 2023target 2027
Gas project PIS092, Utah County
Gas · PacifiCorp
73.0 MWIn study Utah, UTWest Oct 2024target 2026
Gas project PIS093, Juab County
Gas · PacifiCorp
71.0 MWIn study Juab, UTWest Oct 2024target 2026
Solar project C2-168, Emery County
Solar · PacifiCorp
70.0 MWIn study Emery, UTWest May 2022target 2026
Solar project PIS058, Emery County
Solar · PacifiCorp
70.0 MWIn study Emery, UTWest May 2024target 2026

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20132025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)