Requests shown9615.0 GW
Active in queue52.5 GW240 requests
Agreement signed14.4 GW82 requests
Withdrawn467102.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

96 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2003-022, Custer County
Onshore wind
120 MWOperating Custer, OKSPP Dec 20032006
Onshore wind project GEN-2005-008, Harper County
Onshore wind
120 MWOperating Harper, OKSPP Apr 20052007
Solar project GEN-2015-013, Kiowa County
Solar
120 MWOperating Kiowa, OKSPP Mar 20152024
Onshore wind project GEN-2011-040, Murray County
Onshore wind
111 MWOperating Murray, OKSPP Sep 20112014
Onshore wind project GEN-2011-050, Grady County
Onshore wind
108 MWOperating Grady, OKSPP Sep 20112016
Onshore wind project GEN-2017-047, Beaver County
Onshore wind
102 MWOperating Beaver, OKSPP May 20172024
Onshore wind project GEN-2001-037, Woodward County
Onshore wind
102 MWOperating Woodward, OKSPP Oct 20012003
Onshore wind project GEN-2008-003, Woodward County
Onshore wind
101 MWOperating Woodward, OKSPP Jan 20082009
Onshore wind project GEN-2011-010, Caddo County
Onshore wind
101 MWOperating Caddo, OKSPP Mar 20112012
Onshore wind project GEN-2006-002, Beckham County
Onshore wind
101 MWOperating Beckham, OKSPP Jan 20062010
Onshore wind project GEN-2016-028, Le Flore County
Onshore wind
100 MWOperating Le Flore, OKSPP Mar 20162019
Solar project GEN-2017-036, Kiowa County
Solar
100 MWOperating Kiowa, OKSPP May 20172025
Onshore wind project GEN-2013-007, Murray County
Onshore wind
100 MWOperating Murray, OKSPP Mar 20132015
Onshore wind project GEN-2016-097, Caddo County
Onshore wind
100 MWOperating Caddo, OKSPP Oct 20162024
Onshore wind project GEN-2003-004, Caddo County
Onshore wind
100 MWOperating Caddo, OKSPP Jun 20032005
Onshore wind project GEN-2014-020, Grady County
Onshore wind
100 MWOperating Grady, OKSPP Jul 20142017
Onshore wind project GEN-2015-057, Grady County
Onshore wind
100 MWOperating Grady, OKSPP Oct 20152018
Onshore wind project GEN-2008-037, Comanche County
Onshore wind
99.0 MWOperating Comanche, OKSPP May 20082011
Onshore wind project GEN-2006-043, Beckham County
Onshore wind
99.0 MWOperating Beckham, OKSPP Nov 20062009
Onshore wind project GEN-2003-005, Caddo County
Onshore wind
99.0 MWOperating Caddo, OKSPP Jun 20032006
Onshore wind project GEN-2012-033, Garfield County
Onshore wind
98.8 MWOperating Garfield, OKSPP Sep 20122015
Onshore wind project GEN-2001-014, Caddo County
Onshore wind
94.5 MWOperating Caddo, OKSPP Apr 20012007
Battery storage project GEN-2023-SR18, Grady County
Battery storage
80.0 MWOperating Grady, OKSPP Jun 20232025
Onshore wind project GEN-2001-026, Comanche County
Onshore wind
74.3 MWOperating Comanche, OKSPP Jul 20012003
Onshore wind project GEN-2012-028, Washita County
Onshore wind
74.0 MWOperating Washita, OKSPP Sep 20122015
Battery storage project GEN-2023-SR13, Garfield County
Battery storage
70.0 MWOperating Garfield, OKSPP Jan 20232025
Onshore wind project GEN-2009-025, Kay County
Onshore wind
59.8 MWOperating Kay, OKSPP Jun 20092012
Onshore wind project GEN-2012-004, Carter County
Onshore wind
40.8 MWOperating Carter, OKSPP Mar 20122014
Onshore wind project GEN-2005-003, Caddo County
Onshore wind
30.6 MWOperating Caddo, OKSPP Jan 20052005
Onshore wind project GEN-2010-011, Dewey County
Onshore wind
29.7 MWOperating Dewey, OKSPP Mar 20102012
Gas project GEN-2016-009, Kay County
Gas
29.0 MWOperating Kay, OKSPP Mar 20162020
Onshore wind project GEN-2004-020, Custer County
Onshore wind
27.0 MWOperating Custer, OKSPP Oct 20042006
Gas project GEN-2016-047, Canadian County
Gas
24.0 MWOperating Canadian, OKSPP Mar 20162018
Onshore wind project GEN-2004-023, Caddo County
Onshore wind
20.6 MWOperating Caddo, OKSPP Oct 20042005
Onshore wind project GEN-2006-024S, Harper County
Onshore wind
18.9 MWOperating Harper, OKSPP Jul 20062008
Hydro project GEN-2008-005, Mayes County
Hydro
16.0 MWOperating Mayes, OKSPP Jan 20082009
Onshore wind project GEN-2014-002, Dewey County
Onshore wind
10.5 MWOperating Dewey, OKSPP Feb 20142015
Battery storage project GEN-2015-045, Grady County
Battery storage
10.3 MWOperating Grady, OKSPP Oct 20152020
Onshore wind project GEN-2016-051, Custer County
Onshore wind
9.8 MWOperating Custer, OKSPP Mar 20162020
Onshore wind project GEN-2011-037, Caddo County
Onshore wind
6.6 MWOperating Caddo, OKSPP Jul 20112013
Onshore wind project GEN-2016-132, Roger Mills County
Onshore wind
6.1 MWOperating Roger Mills, OKSPP Nov 20162020
Onshore wind project GEN-2014-005, Caddo County
Onshore wind
5.7 MWOperating Caddo, OKSPP Feb 20142015
Onshore wind project GEN-2015-062, Garfield County
Onshore wind
4.5 MWOperating Garfield, OKSPP Oct 20152024
Gas project GEN-2010-055, Tulsa County
Gas
4.5 MWOperating Tulsa, OKSPP Sep 20102013
Onshore wind project GEN-2016-131, Grady County
Onshore wind
2.5 MWOperating Grady, OKSPP Nov 20162021
Onshore wind project GEN-2016-031, Kay County
Onshore wind
1.5 MWOperating Kay, OKSPP Mar 20162016
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)