πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Indiana (2025 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6518.3 GW
Active in queue18.3 GW65 requests
Agreement signed0.0 MW0 requests
Withdrawn213,029 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

65 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar + storage project AG2-519, Delaware County
Solar + storage Β· Muncie Solar 1, LLC
66.5 MWIn study Delaware, INPJM Mar 2025target 2024
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030
Gas project AG2-562, St. Joseph County
Gas Β· St. Joseph Energy Center, LLC
52.0 MWIn study St. Joseph, INPJM May 2025target 2022
Battery storage project AG2-370, Allen County
Battery storage Β· Tillman Storage LLC
50.0 MWIn study Allen, INPJM Mar 2025target 2024
Battery storage project AG2-551, Randolph County
Battery storage Β· Riverstart Solar Park VI LLC
50.0 MWIn study Randolph, INPJM Feb 2025target 2024
Solar project AH1-153, St. Joseph County
Solar Β· Dumont Solar, LLC
50.0 MWIn study St. Joseph, INPJM Mar 2025target 2025
Battery storage project S1126, Knox County
Battery storage
50.0 MWIn study Knox, INMISO Oct 2025target 2029
Battery storage project AG2-345, Fountain County
Battery storage Β· Dolphin Solar LLC
50.0 MWIn study Fountain, INPJM Feb 2025target 2024
Battery storage project AG2-014, White County
Battery storage Β· Black Prairie Storage LLC
50.0 MWIn study White, INPJM Feb 2025target 2023
Battery storage project AG2-492, White County
Battery storage Β· Black Prairie Storage II LLC
50.0 MWIn study White, INPJM Feb 2025target 2024
Solar + storage project AG2-191, Grant County
Solar + storage Β· BR Solar Sheriff 2 LLC
30.0 MWIn study Grant, INPJM Feb 2025target 2023
Solar + storage project AG2-192, Grant County
Solar + storage Β· BR Solar Sheriff 2 LLC
19.0 MWIn study Grant, INPJM Feb 2025target 2023
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)