Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6913.8 GW
Active in queue13.8 GW69 requests
Agreement signed0.0 MW0 requests
Withdrawn6710.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

69 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3754, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Onshore wind project J3755, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Onshore wind project J2311, Putnam County
Onshore wind
145 MWIn study Putnam, ILMISO Oct 2024target 2024
Solar project J3797, Edgar County
Solar
141 MWIn study Edgar, ILMISO Apr 2024target 2028
Solar project J3611, Hamilton County
Solar
140 MWIn study Hamilton, ILMISO Apr 2024target 2026
Onshore wind project J3820, Hancock County
Onshore wind
127 MWIn study Hancock, ILMISO Apr 2024target 2028
Solar project J3687, Fayette County
Solar
113 MWIn study Fayette, ILMISO Apr 2024target 2027
Onshore wind project J3602, Mclean County
Onshore wind
110 MWIn study Mclean, ILMISO Apr 2024target 2028
Onshore wind project J3456, Tazewell County
Onshore wind
100 MWIn study Tazewell, ILMISO Apr 2024target 2028
Solar project J3674, Jasper County
Solar
100 MWIn study Jasper, ILMISO Apr 2024target 2028
Battery storage project J3565, Champaign County
Battery storage
100 MWIn study Champaign, ILMISO Apr 2024target 2028
Solar project J3916, Saline County
Solar
100 MWIn study Saline, ILMISO Oct 2024target 2030
Solar project J3685, Pike County
Solar
100 MWIn study Pike, ILMISO Apr 2024target 2028
Solar project J3899, Putnam County
Solar
100 MWIn study Putnam, ILMISO Dec 2024target 2027
Battery storage project J3344, Knox County
Battery storage
100 MWIn study Knox, ILMISO Apr 2024target 2028
Solar project J3379, Johnson County
Solar
100 MWIn study Johnson, ILMISO Apr 2024target 2028
Onshore wind project J3341, Vermilion County
Onshore wind
100 MWIn study Vermilion, ILMISO Apr 2024target 2028
Onshore wind project J2312, Putnam County
Onshore wind
47.9 MWIn study Putnam, ILMISO Oct 2024target 2024
Solar project J3818, Shelby County
Solar
40.0 MWIn study Shelby, ILMISO Jun 2024target 2028
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)