United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2019 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7221.7 GW
Active in queue21.7 GW72 requests
Agreement signed3,861 MW26 requests
Withdrawn24741.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

72 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q297, Yuma County
Battery storage
90.1 MWIn study Yuma, AZWest Mar 2019target 2022
Solar project G0626, Grant County
Solar
90.0 MWIn study Grant, WAWest Jun 2019target 2022
Solar + storage project TCS-44, Crook County
Solar + storage Β· Three Springs Interconnection B LLC
80.0 MWAgreement signed Crook, ORWest Sep 2019target 2027
Onshore wind project IA-PNM-2019-12, Torrance County
Onshore wind
80.0 MWIn study Torrance, NMWest Apr 2019target 2020
Solar project QF19-081, Jefferson County
Solar
53.0 MWAgreement signed Jefferson, ORWest Nov 2019target 2022
Battery storage project Company JV, Carson City County
Battery storage
50.0 MWAgreement signed Carson City, NVWest Mar 2019target 2023
Battery storage project Q315, Coconino County
Battery storage
50.0 MWPaused / redesign Coconino, AZWest Sep 2019target 2022
VE50S Project
Solar + storage
50.0 MWAgreement signed Dona Ana, NMWest Sep 2019target 2026
Solar + storage project 562, Malheur County
Solar + storage Β· Moores Hollow PV1, LLC
42.0 MWPaused / redesign Malheur, ORWest Aug 2019target 2024
Solar + storage project TCS-45, Crook County
Solar + storage Β· Three Springs Interconnection C LLC
40.0 MWAgreement signed Crook, ORWest Sep 2019target 2028
Solar project 103, Lincoln County
Solar
40.0 MWIn study Lincoln, WAWest Dec 2019target 2021
Solar + storage project TCS-43, Crook County
Solar + storage Β· Three Springs Interconnection A LLC
40.0 MWAgreement signed Crook, ORWest Sep 2019target 2027
Solar + storage project 556, Grant County
Solar + storage Β· Prairie City PV1, LLC
30.0 MWPaused / redesign Grant, ORWest Apr 2019target 2024
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Gas project G0620, Umatilla County
Gas
27.0 MWIn study Umatilla, ORWest Apr 2019target 2019
Solar project GI-2019-5, Garfield County
Solar
19.9 MWIn study Garfield, COWest Apr 2019target 2020
Solar project 85, Adams County
Solar
5.0 MWIn study Adams, WAWest Apr 2019target 2020
Solar + storage project 84, Stevens County
Solar + storage
5.0 MWIn study Stevens, WAWest Apr 2019target 2024
Hydro project 1186, Bannock County
Hydro Β· Commercial Energy Management, Inc.
0.9 MWAgreement signed Bannock, IDWest Oct 2019target 2021
Solar project TCS-40, Benton County
Solar Β· Oregon State University
0.8 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-38, Benton County
Solar Β· Oregon State University
0.3 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-39, Benton County
Solar Β· Oregon State University
0.2 MWAgreement signed Benton, ORWest Jul 2019target 2024
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)