United States › Grid › Interconnection queues › Virginia

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Virginia — page 18

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown86886.8 GW
Active in queue30.3 GW287 requests
Agreement signed7,318 MW72 requests
Withdrawn86886.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

868 requests · page 18 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Saltville-Holston 34.5kV Solar Facility
Solar
5.0 MWWithdrawn / abandoned Smyth, VAPJM Dec 2015target 2017
Pulaski Community Solar
Solar
5.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
Boykins Solar
Solar
4.5 MWWithdrawn / abandoned Southampton, VAPJM Mar 2015target 2017
Battery storage project AH1-142, Henrico County
Battery storage
4.0 MWWithdrawn / abandoned Henrico, VAPJM Aug 2021target 2024
Offshore wind project AD1-089, City Of Virginia Beach County
Offshore wind
4.0 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Sep 2017target 2020
Battery storage project AB2-030, Accomack County
Battery storage
4.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2016target 2016
Other project X2-061, Brunswick County
Other
4.0 MWWithdrawn / abandoned Brunswick, VAPJM Jun 2011target 2012
Solar project AG2-393, Buckingham County
Solar
3.0 MWWithdrawn / abandoned Buckingham, VAPJM Mar 2021target 2022
CO-Zaners Rohrsburg
Solar + storage
3.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2024
Solar + storage project AH2-182, Rockingham County
Solar + storage
3.0 MWWithdrawn / abandoned Rockingham, VAPJM Mar 2022target 2024
LH Church
Solar + storage
3.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2024
Battery storage project AB1-022, Louisa County
Battery storage
2.0 MWWithdrawn / abandoned Louisa, VAPJM Jul 2015target 2017
Battery storage project AH1-143, Henrico County
Battery storage
2.0 MWWithdrawn / abandoned Henrico, VAPJM Aug 2021target 2024
Fauquier County Landfill Units 1 & 2
Other
2.0 MWWithdrawn / abandoned Fauquier, VAPJM Oct 2012target 2016
Solar + storage project AH2-251, Rockingham County
Solar + storage
2.0 MWWithdrawn / abandoned Rockingham, VAPJM Mar 2022target 2024
CO-Ridge
Solar + storage
2.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2024
Other project AA2-185, Prince William County
Other
1.6 MWWithdrawn / abandoned Prince William, VAPJM Apr 2015target 2016
Other project W3-010, Montgomery County
Other
0.3 MWWithdrawn / abandoned Montgomery, VAPJM Aug 2010target 2010
Page 18 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)