BATTERY STORAGE Β· PJM

Battery storage project AH1-142, Henrico County

Battery storage project AH1-142, Henrico County is a 4.0 MW battery storage request withdrawn in the PJM interconnection queue, in Henrico County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-142
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Darbytown 230 kV II
Location
Henrico County, Virginia
Technology
Battery: 4.0 MW
Total requested
4.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
27 August 2021
Proposed online date
December 2024
Withdrawn
December 2024

Location

Marker shows the centre of Henrico County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Henrico County