Queue requests in study in the USA — page 135

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 135 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-394, Lawrence County
Solar
6.3 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project AH2-389, Lawrence County
Solar
6.0 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project J4169, Dickinson County
Solar
6.0 MWIn study Dickinson, MIMISO Oct 2025target 2025
Solar project 977121, Williamsburg County
Solar
6.0 MWIn study Williamsburg, SCSoutheast Jun 2025
Nuclear project 625, Limestone County
Nuclear
6.0 MWIn study Limestone, ALSoutheast Jun 2024target 2028
Wind + storage project C1-04, Salt Lake County
Wind + storage
6.0 MWIn study Salt Lake, UTWest Apr 2021target 2023
Solar project AI1-122, Sussex County
Solar
5.9 MWIn study Sussex, NJPJM Sep 2022target 2025
Solar project AI2-458, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-476, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AH2-042, Berkeley County
Solar
5.8 MWIn study Berkeley, WVPJM Nov 2021target 2024
Solar project AI2-467, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-469, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-459, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-470, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-477, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AH2-039, Marion County
Solar
5.5 MWIn study Marion, WVPJM Nov 2021target 2024
Solar project AI2-312, Venango County
Solar
5.5 MWIn study Venango, PAPJM Mar 2023target 2022
Furnace View Farms
Solar
5.0 MWPaused / redesign Berks, PAPJM Sep 2020target 2023
Solar project 977893, Robeson County
Solar
5.0 MWIn study Robeson, NCSoutheast Jun 2025
Solar project AI2-043, Northumberland County
Solar
5.0 MWIn study Northumberland, VAPJM Jan 2023target 2024
Solar project 85, Adams County
Solar
5.0 MWIn study Adams, WAWest Apr 2019target 2020
Gas project PP00021, Wayne County
Gas
5.0 MWIn study Wayne, NCSoutheast Apr 2025target 2028
Solar project AI2-017, Centre County
Solar
5.0 MWIn study Centre, PAPJM Dec 2022target 2026
Solar Increase
Solar
5.0 MWIn study Hartford, CTISO-NE Feb 2023target 2027
Solar project 977895, Durham County
Solar
5.0 MWIn study Durham, NCSoutheast Jun 2025
Solar project AH2-101, Prince Edward County
Solar
5.0 MWIn study Prince Edward, VAPJM Jan 2022target 2023
Solar project 977876, Williamsburg County
Solar
5.0 MWIn study Williamsburg, SCSoutheast Jun 2025
Solar project 977894, Robeson County
Solar
5.0 MWIn study Robeson, NCSoutheast Jun 2025
Solar project 977864, Florence County
Solar
5.0 MWIn study Florence, SCSoutheast Jun 2025
Gas project PP00022, Wayne County
Gas
5.0 MWIn study Wayne, NCSoutheast Apr 2025target 2028
Solar project AH2-062, Chester County
Solar
5.0 MWIn study Chester, PAPJM Dec 2021target 2023
Gas project 957688, Buncombe County
Gas · Duke Energy Progress LLC
5.0 MWIn study Buncombe, NCSoutheast Jun 2024
Solar + storage project 84, Stevens County
Solar + storage
5.0 MWIn study Stevens, WAWest Apr 2019target 2024
Solar project AH2-036, Bradford County
Solar
5.0 MWIn study Bradford, PAPJM Nov 2021target 2023
Solar project AH2-066, Jefferson County
Solar
5.0 MWIn study Jefferson, PAPJM Jan 2022target 2023
Gas project 957517, Anderson County
Gas
5.0 MWIn study Anderson, SCSoutheast Jun 2024
Solar project AI2-019, Franklin County
Solar
5.0 MWIn study Franklin, PAPJM Dec 2022target 2026
Gas project 957514, Anderson County
Gas
5.0 MWIn study Anderson, SCSoutheast Jun 2024
Solar project 977888, Rockingham County
Solar
5.0 MWIn study Rockingham, NCSoutheast Jun 2025
Solar project AI1-030, Erie County
Solar
5.0 MWIn study Erie, PAPJM Apr 2022target 2024
Solar project 977879, Florence County
Solar
5.0 MWIn study Florence, SCSoutheast Jun 2025
Solar project AH2-014, Erie County
Solar
5.0 MWIn study Erie, PAPJM Oct 2021target 2024
Gas project PP00023, Wayne County
Gas
5.0 MWIn study Wayne, NCSoutheast Apr 2025target 2029
Solar project 968459, Darlington County
Solar
5.0 MWIn study Darlington, SCSoutheast Jan 2025
Solar project 957087, Florence County
Solar
5.0 MWIn study Florence, SCSoutheast Jun 2024
Gas project 456, Brown County
Gas
5.0 MWIn study Brown, SDWest Feb 2024target 2025
Gas project PP00019, Buncombe County
Gas
5.0 MWIn study Buncombe, NCSoutheast Apr 2025target 2026
Solar project AH2-023, Mercer County
Solar
5.0 MWIn study Mercer, PAPJM Oct 2021target 2024
Solar project 977889, Scotland County
Solar
5.0 MWIn study Scotland, NCSoutheast Jun 2025
Gas project 957692, Wayne County
Gas · Duke Energy Progress LLC
5.0 MWIn study Wayne, NCSoutheast Jun 2024
Page 135 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)