Solar project 977893, Robeson County

Solar project 977893, Robeson County is a 5.0 MW solar request in interconnection study in the Southeast interconnection queue, in Robeson County, North Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
977893
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
MAXTON 115KV
Location
Robeson County, North Carolina
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Other
Study phase
Phase 1 Cluster Study - Study Complete
Queue status
Active
Entered queue
30 June 2025

Location

Marker shows the centre of Robeson County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Robeson County