OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 12 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 730, Morrow County
Solar + storage
450 MWWithdrawn / abandoned Morrow, ORWest Jul 2023target 2027
Orion Energy LLC
Onshore wind · Orion Energy, LLC
450 MWWithdrawn / abandoned Wasco, ORWest Mar 2004target 2006
Onshore wind project TCS-47, Bingham County
Onshore wind
450 MWWithdrawn / abandoned Bingham, IDWest Oct 2019target 2023
Solar + storage project C3-181, Morrow County
Solar + storage
450 MWWithdrawn / abandoned Morrow, ORWest May 2023target 2027
Onshore wind project 1172, Bingham County
Onshore wind
450 MWWithdrawn / abandoned Bingham, IDWest Oct 2019target 2022
Solar + storage project IA-PNM-2019-15, Bernalillo County
Solar + storage
450 MWWithdrawn / abandoned Bernalillo, NMWest Apr 2019target 2024
Solar project GI-2019-1, El Paso County
Solar
450 MWWithdrawn / abandoned El Paso, COWest Feb 2019target 2021
Tenaska Inc
Gas · Tenaska, Inc.
450 MWWithdrawn / abandoned Klamath, ORWest Mar 2001target 2004
Solar + storage project Company KF, Pershing County
Solar + storage
450 MWWithdrawn / abandoned Pershing, NVWest Oct 2019target 2022
Solar project G0610, Sherman County
Solar
450 MWWithdrawn / abandoned Sherman, ORWest Jan 2019target 2021
Solar + storage project IA-PNM-2025-21, San Juan County
Solar + storage
450 MWWithdrawn / abandoned San Juan, NMWest Mar 2025target 2029
Solar + storage project C3-137, San Juan County
Solar + storage
450 MWWithdrawn / abandoned San Juan, NMWest May 2023target 2027
Other project G0855, Umatilla County
Other
450 MWWithdrawn / abandoned Umatilla, ORWest Apr 2023target 2027
Solar + storage project Q531, Maricopa County
Solar + storage
441 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar project Q04, Maricopa County
Solar
440 MWWithdrawn / abandoned Maricopa, AZWest Apr 2009target 2013
Solar project Company 148, Clark County
Solar
440 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2018
Solar project Q03, Maricopa County
Solar
440 MWWithdrawn / abandoned Maricopa, AZWest Oct 2008target 2013
Gas project 134, Carbon County
Gas · Clipper Windpower Development Company, Inc.
430 MWWithdrawn / abandoned Carbon, WYWest May 2007target 2010
Solar + storage project Company 180, Clark County
Solar + storage
425 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Onshore wind project G0391, Gilliam County
Onshore wind
425 MWWithdrawn / abandoned Gilliam, ORWest Nov 2009target 2013
Solar + storage project 2022-G8
Solar + storage
422 MWWithdrawn / abandoned West Jul 2022target 2025
Solar + storage project Company OK, Esmeralda County
Solar + storage
420 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2026
Solar + storage project Q2416, Maricopa County
Solar + storage
420 MWWithdrawn / abandoned Maricopa, AZWest Feb 2024target 2029
Onshore wind project G0304, Harney County
Onshore wind
416 MWWithdrawn / abandoned Harney, ORWest Jan 2008target 2009
Battery storage project 711, Klamath County
Battery storage
416 MWWithdrawn / abandoned Klamath, ORWest Sep 2015target 2022
Battery storage project G0751, Sherman County
Battery storage
413 MWWithdrawn / abandoned Sherman, ORWest Jun 2022target 2025
Gas project G0452, Umatilla County
Gas
410 MWWithdrawn / abandoned Umatilla, ORWest May 2011target 2015
Solar + storage project Q343, Maricopa County
Solar + storage
410 MWWithdrawn / abandoned Maricopa, AZWest Mar 2020target 2023
Onshore wind project Q86, Navajo County
Onshore wind
407 MWWithdrawn / abandoned Navajo, AZWest Nov 2021target 2025
Battery storage project Q99, Pinal County
Battery storage
406 MWWithdrawn / abandoned Pinal, AZWest Sep 2022target 2025
Solar + storage project Q2505, Maricopa County
Solar + storage
405 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2028
Solar + storage project Q2504, Maricopa County
Solar + storage
405 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2028
Solar + storage project Q88, Pinal County
Solar + storage
405 MWWithdrawn / abandoned Pinal, AZWest Dec 2021target 2023
Onshore wind project 295, Carbon County
Onshore wind
403 MWWithdrawn / abandoned Carbon, WYWest Oct 2009target 2014
Solar + storage project 762, Elmore County
Solar + storage
402 MWWithdrawn / abandoned Elmore, IDWest Mar 2025
Onshore wind project C4-020, San Juan County
Onshore wind
402 MWWithdrawn / abandoned San Juan, UTWest May 2024target 2028
Onshore wind project GI-2004-5, Weld County
Onshore wind
402 MWWithdrawn / abandoned Weld, COWest Aug 2004target 2006
Coal project Q21, Navajo County
Coal
401 MWWithdrawn / abandoned Navajo, AZWest Mar 2006target 2008
Onshore wind project G0581, Morrow County
Onshore wind
401 MWWithdrawn / abandoned Morrow, ORWest Feb 2018target 2020
Onshore wind project GI-2018-10, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-7, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-12, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-8, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project 76, Union County
Onshore wind
401 MWWithdrawn / abandoned Union, ORWest Apr 2002target 2003
Onshore wind project GI-2023-15, Morgan County
Onshore wind
401 MWWithdrawn / abandoned Morgan, COWest May 2023target 2026
Solar + storage project 718, Lake County
Solar + storage
400 MWWithdrawn / abandoned Lake, ORWest Nov 2015target 2019
Solar + storage project G0672, Benton County
Solar + storage
400 MWWithdrawn / abandoned Benton, WAWest Mar 2021target 2024
Solar + storage project Q515, Yuma County
Solar + storage
400 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2027
Other project G0906, Linn County
Other
400 MWWithdrawn / abandoned Linn, ORWest Jun 2023target 2030
Battery storage project 1166, Box Elder County
Battery storage
400 MWWithdrawn / abandoned Box Elder, UTWest Sep 2019target 2021
Page 12 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)