United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) — page 12
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project 730, Morrow County Solar + storage |
450 MW | Withdrawn / abandoned |
| Orion Energy LLC Onshore wind · Orion Energy, LLC |
450 MW | Withdrawn / abandoned |
| Onshore wind project TCS-47, Bingham County Onshore wind |
450 MW | Withdrawn / abandoned |
| Solar + storage project C3-181, Morrow County Solar + storage |
450 MW | Withdrawn / abandoned |
| Onshore wind project 1172, Bingham County Onshore wind |
450 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2019-15, Bernalillo County Solar + storage |
450 MW | Withdrawn / abandoned |
| Solar project GI-2019-1, El Paso County Solar |
450 MW | Withdrawn / abandoned |
| Tenaska Inc Gas · Tenaska, Inc. |
450 MW | Withdrawn / abandoned |
| Solar + storage project Company KF, Pershing County Solar + storage |
450 MW | Withdrawn / abandoned |
| Solar project G0610, Sherman County Solar |
450 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2025-21, San Juan County Solar + storage |
450 MW | Withdrawn / abandoned |
| Solar + storage project C3-137, San Juan County Solar + storage |
450 MW | Withdrawn / abandoned |
| Other project G0855, Umatilla County Other |
450 MW | Withdrawn / abandoned |
| Solar + storage project Q531, Maricopa County Solar + storage |
441 MW | Withdrawn / abandoned |
| Solar project Q04, Maricopa County Solar |
440 MW | Withdrawn / abandoned |
| Solar project Company 148, Clark County Solar |
440 MW | Withdrawn / abandoned |
| Solar project Q03, Maricopa County Solar |
440 MW | Withdrawn / abandoned |
| Gas project 134, Carbon County Gas · Clipper Windpower Development Company, Inc. |
430 MW | Withdrawn / abandoned |
| Solar + storage project Company 180, Clark County Solar + storage |
425 MW | Withdrawn / abandoned |
| Onshore wind project G0391, Gilliam County Onshore wind |
425 MW | Withdrawn / abandoned |
| Solar + storage project 2022-G8 Solar + storage |
422 MW | Withdrawn / abandoned |
| Solar + storage project Company OK, Esmeralda County Solar + storage |
420 MW | Withdrawn / abandoned |
| Solar + storage project Q2416, Maricopa County Solar + storage |
420 MW | Withdrawn / abandoned |
| Onshore wind project G0304, Harney County Onshore wind |
416 MW | Withdrawn / abandoned |
| Battery storage project 711, Klamath County Battery storage |
416 MW | Withdrawn / abandoned |
| Battery storage project G0751, Sherman County Battery storage |
413 MW | Withdrawn / abandoned |
| Gas project G0452, Umatilla County Gas |
410 MW | Withdrawn / abandoned |
| Solar + storage project Q343, Maricopa County Solar + storage |
410 MW | Withdrawn / abandoned |
| Onshore wind project Q86, Navajo County Onshore wind |
407 MW | Withdrawn / abandoned |
| Battery storage project Q99, Pinal County Battery storage |
406 MW | Withdrawn / abandoned |
| Solar + storage project Q2505, Maricopa County Solar + storage |
405 MW | Withdrawn / abandoned |
| Solar + storage project Q2504, Maricopa County Solar + storage |
405 MW | Withdrawn / abandoned |
| Solar + storage project Q88, Pinal County Solar + storage |
405 MW | Withdrawn / abandoned |
| Onshore wind project 295, Carbon County Onshore wind |
403 MW | Withdrawn / abandoned |
| Solar + storage project 762, Elmore County Solar + storage |
402 MW | Withdrawn / abandoned |
| Onshore wind project C4-020, San Juan County Onshore wind |
402 MW | Withdrawn / abandoned |
| Onshore wind project GI-2004-5, Weld County Onshore wind |
402 MW | Withdrawn / abandoned |
| Coal project Q21, Navajo County Coal |
401 MW | Withdrawn / abandoned |
| Onshore wind project G0581, Morrow County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-10, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-7, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-12, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-8, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project 76, Union County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2023-15, Morgan County Onshore wind |
401 MW | Withdrawn / abandoned |
| Solar + storage project 718, Lake County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project G0672, Benton County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q515, Yuma County Solar + storage |
400 MW | Withdrawn / abandoned |
| Other project G0906, Linn County Other |
400 MW | Withdrawn / abandoned |
| Battery storage project 1166, Box Elder County Battery storage |
400 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)