United States › Grid › Interconnection queues › Utah
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Utah — page 11
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project C3-092, Tooele County Solar · PacifiCorp |
19.9 MW | Withdrawn / abandoned |
| Geothermal project S0032, Beaver County Geothermal |
19.2 MW | Withdrawn / abandoned |
| Other project 637, Salt Lake County Other |
18.0 MW | Withdrawn / abandoned |
| Solar project 733, Washington County Solar |
18.0 MW | Withdrawn / abandoned |
| Gas project PIS059, Salt Lake County Gas · PacifiCorp |
17.0 MW | Withdrawn / abandoned |
| Gas project C4-060, Salt Lake County Gas · PacifiCorp |
17.0 MW | Withdrawn / abandoned |
| Onshore wind project 397, Washington County Onshore wind |
16.0 MW | Withdrawn / abandoned |
| Solar project 293-B, Weber County Solar |
15.0 MW | Withdrawn / abandoned |
| Other project 627, Salt Lake County Other |
15.0 MW | Withdrawn / abandoned |
| Solar project 311, Iron County Solar · Cedar Solar Energy, LLC |
14.0 MW | Withdrawn / abandoned |
| Geothermal project 235, Millard County Geothermal |
14.0 MW | Withdrawn / abandoned |
| Geothermal project 231-B, Beaver County Geothermal |
14.0 MW | Withdrawn / abandoned |
| Onshore wind project 345-A, Washington County Onshore wind |
14.0 MW | Withdrawn / abandoned |
| Hydro project 45, Wasatch County Hydro |
12.0 MW | Withdrawn / abandoned |
| Solar project 797, Box Elder County Solar |
12.0 MW | Withdrawn / abandoned |
| Other project 404, Sanpete County Other |
11.8 MW | Withdrawn / abandoned |
| Hydro project 617, Utah County Hydro |
11.5 MW | Withdrawn / abandoned |
| Hydro project 656, Utah County Hydro |
11.5 MW | Withdrawn / abandoned |
| Hydro project 645, Utah County Hydro |
11.5 MW | Withdrawn / abandoned |
| Geothermal project 162, Beaver County Geothermal |
11.0 MW | Withdrawn / abandoned |
| Geothermal project 212-B, Beaver County Geothermal |
11.0 MW | Withdrawn / abandoned |
| Geothermal project 212-A, Beaver County Geothermal |
11.0 MW | Withdrawn / abandoned |
| Onshore wind project 70, Utah County Onshore wind |
10.5 MW | Withdrawn / abandoned |
| Onshore wind project 49, Utah County Onshore wind |
10.5 MW | Withdrawn / abandoned |
| Solar project 649, Washington County Solar |
10.3 MW | Withdrawn / abandoned |
| Solar project 622, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 990, Tooele County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 293-C, Weber County Solar · Shamrock Wind, LLC |
10.0 MW | Withdrawn / abandoned |
| Solar project 880, Tooele County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 989, Tooele County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar + storage project C3-072, Box Elder County Solar + storage |
10.0 MW | Withdrawn / abandoned |
| Solar project 623, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 561, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar + storage project C3-073, Box Elder County Solar + storage |
10.0 MW | Withdrawn / abandoned |
| Solar project 1003, Tooele County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 680, Iron County Solar |
8.0 MW | Withdrawn / abandoned |
| Other project 160, Washington County Other · Intermountain Renewable Power, LLC |
7.5 MW | Withdrawn / abandoned |
| Gas project 347, Washington County Gas · AG Hydro, LLC |
7.5 MW | Withdrawn / abandoned |
| Other project 655, Davis County Other · Georgia-Pacific Consumer Projects (Camas), LLC |
7.1 MW | Withdrawn / abandoned |
| Geothermal project 242, Beaver County Geothermal |
7.0 MW | Withdrawn / abandoned |
| Gas project 619, Salt Lake County Gas |
6.3 MW | Withdrawn / abandoned |
| Other project 524, Salt Lake County Other |
6.0 MW | Withdrawn / abandoned |
| Other project 523, Utah County Other |
6.0 MW | Withdrawn / abandoned |
| Gas project 77, Salt Lake County Gas |
5.8 MW | Withdrawn / abandoned |
| Solar project 1140, Salt Lake County Solar |
5.5 MW | Withdrawn / abandoned |
| Solar project 584-B, Utah County Solar |
5.2 MW | Withdrawn / abandoned |
| Hydro project 340, Washington County Hydro |
5.2 MW | Withdrawn / abandoned |
| Other project C3-151, Millard County Other |
5.0 MW | Withdrawn / abandoned |
| Solar project C3-071, Box Elder County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project C3-089, Washington County Solar + storage · PacifiCorp |
5.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)