WIND Β· OPERATIONAL

Weston

Weston is a 4 MW onshore wind farm in East of England, England, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East of England
  • England
Project stageOperating
  1. PlanningAug 2010 (completed)
  2. ConsentedJan 2012 (completed)
  3. ConstructionJan 2014 (completed)
  4. OperatingMar 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Temporis Capital
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PE37 8JX
Coordinates
52.6953, 1.0915

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Weston compares

433rd of 488largest wind farms in the UK register
38th of 48in East of England
0.01%of listed UK wind farms capacity
β‰ˆ 9.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 4 MW station would generate roughly 9.1 GWh of electricity in a year, similar to the annual use of about 3,370 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East of England All run by Temporis Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Weston Airfield Wind Turbines
Developer / operator
Bernard Matthews
Planning authority
Broadland
Planning reference
20101283
Application submitted
17 August 2010
Permission granted
23 January 2012
Construction started
26 January 2014
Began operating
15 March 2015
Capacity in planning record
3.6 MW
Address
The Old Airfield, Airfield Lane, Weston Longville, Norfolk, NR9 5JF
REPD reference
3354

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026