Sheringham Shoal BMU 1 is a 158 MW offshore wind farm in East of England, England, operated by Scira Offshore Energy. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Offshore
  • East of England
  • England
Project stageOperating
  1. PlanningMay 2006 (completed)
  2. ConsentedAug 2008 (completed)
  3. ConstructionJun 2009 (completed)
  4. OperatingOct 2012 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
158 MW
Status
Operational
Technology
Wind Β· Offshore
Operator
Scira Offshore Energy
Region
East of England
Country
England
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
53.1353, 1.1479

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Sheringham Shoal BMU 1 compares

40th of 488largest wind farms in the UK register
7th of 48in East of England
0.54%of listed UK wind farms capacity
β‰ˆ 526 GWhillustrative output a year

At a typical UK load factor for this technology (about 38% of the maximum possible output), a 158 MW station would generate roughly 526 GWh of electricity in a year, similar to the annual use of about 194,800 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East of England All run by Scira Offshore Energy

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Sheringham ShoalΒ 
Developer / operator
Equinor
Planning authority
DECC (S36)
Application submitted
30 May 2006
Permission granted
7 August 2008
Construction started
30 June 2009
Began operating
29 October 2012
Capacity in planning record
317 MW
Address
between 17 and 22 kilometres off the Norfolk coast, north of the seaside town of Sheringham., Offshore
REPD reference
2512

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.