WIND Β· OPERATIONAL

North Hoyle

North Hoyle is a 60 MW offshore wind farm in Wales, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Offshore
  • Wales
Project stageOperating
  1. PlanningApr 2001 (completed)
  2. ConsentedJul 2002 (completed)
  3. ConstructionApr 2003 (completed)
  4. OperatingDec 2003 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
60 MW
Status
Operational
Technology
Wind Β· Offshore
Operator
RWE Npower
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Coordinates
53.4172, -3.4486

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How North Hoyle compares

91st of 488largest wind farms in the UK register
5th of 43in Wales
0.20%of listed UK wind farms capacity
β‰ˆ 200 GWhillustrative output a year

At a typical UK load factor for this technology (about 38% of the maximum possible output), a 60 MW station would generate roughly 200 GWh of electricity in a year, similar to the annual use of about 73,970 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Wales All run by RWE Npower

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
North HoyleΒ 
Developer / operator
Greencoat (formerly Npower Renewables)
Planning authority
DECC (S36)
Application submitted
5 April 2001
Permission granted
31 July 2002
Construction started
3 April 2003
Began operating
1 December 2003
Capacity in planning record
60 MW
Address
7.5km Prestatyn & RhylΒ , Offshore
REPD reference
2494

Full project profile β†’

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.