WIND Β· OPERATIONAL

Minnygap (GB)

Minnygap (GB) is a 25 MW onshore wind farm in Scotland, operated by RES Group. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningJun 2009 (completed)
  2. ConsentedJun 2014 (completed)
  3. ConstructionNov 2015 (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
25 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
RES Group
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Postcode
DG10 9PX
Coordinates
55.2620, -3.4600

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Minnygap (GB) compares

196th of 488largest wind farms in the UK register
121st of 199in Scotland
0.08%of listed UK wind farms capacity
β‰ˆ 57 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 25 MW station would generate roughly 57 GWh of electricity in a year, similar to the annual use of about 21,090 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by RES Group

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Minnygap
Developer / operator
Minnygap (formerly RES)
Planning authority
Dumfries and Galloway
Planning reference
09/P/3/0340
Application submitted
29 June 2009
Permission granted
20 June 2014
Construction started
1 November 2015
Began operating
15 March 2017
Capacity in planning record
25 MW
Address
Nr Annandale, Dumfries and Galloway
REPD reference
4437

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.