WIND Β· OPERATIONAL

Lochhead

Lochhead is a 6 MW onshore wind farm in Scotland, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland

Key facts

Installed capacity
6 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Temporis Capital
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
ML9 3PP
Coordinates
55.6959, -3.9823

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Lochhead compares

394th of 488largest wind farms in the UK register
184th of 199in Scotland
0.02%of listed UK wind farms capacity
β‰ˆ 14 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 6 MW station would generate roughly 14 GWh of electricity in a year, similar to the annual use of about 5,060 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Temporis Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Lochhead Farm
Developer / operator
A7 Energy / Green Energy
Planning authority
South Lanarkshire
Planning reference
HM/05/0147
Application submitted
1 April 2005
Permission granted
1 May 2006
Began operating
1 July 2009
Capacity in planning record
6 MW
Address
Land at Lochhead Farm , Stonehouse, Strathclyde
REPD reference
3453

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026