Lindhurst is a 9 MW onshore wind farm in East Midlands England, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- East Midlands
- England
Key facts
- Installed capacity
- 9 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- RWE Npower
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 53.1175, -1.1516
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Lindhurst compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 9 MW station would generate roughly 20 GWh of electricity in a year, similar to the annual use of about 7,590 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in East Midlands All run by RWE NpowerNearby generating sites
- Stud Farm Β· 2.37 MW solar farm8.4 km
- Bilsthorpe Β· 5.74 MW solar farm8.9 km
- Crow Trees Solar Farm Β· 4.69 MW solar farm9.7 km
- Bilsthorpe Β· 10.3 MW onshore wind farm9.9 km
- Eakring Β· 11.8 MW solar farm10.1 km
- Ollerton Β· 4.25 MW solar farm10.1 km
- 30Acres Β· 3.77 MW solar farm10.3 km
- Welbeck Β· 11.3 MW solar farm11.9 km
Also operated by RWE Npower
RWE Npower operates 90 sites in the register. Largest first:
- Pembroke Β· gas-fired power station2,199 MW
- Didcot A Power Station Β· coal-fired power station2,000 MW
- Staythorpe Β· CCGT gas power station1,828 MW
- Didcot B Β· gas-fired power station1,450 MW
- Tilbury B Power Station Β· coal-fired power station1,050 MW
- Triton Knoll Β· offshore wind farm857 MW
- Little Barford Β· CCGT gas power station735 MW
- London Array Β· offshore wind farm630 MW
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Lindhurst Wind Farm
- Developer / operator
- Npower Renewables
- Planning authority
- Newark and Sherwood
- Planning reference
- 06/01014/FULM
- Application submitted
- 1 June 2006
- Permission granted
- 21 September 2007
- Construction started
- 1 January 2010
- Began operating
- 4 November 2010
- Capacity in planning record
- 15 MW
- Address
- Lindhurst, South of Mansfield, Nottinghamshire
- REPD reference
- 2938
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.