WIND Β· OPERATIONAL

Cruach Mhor

Cruach Mhor is a 29.8 MW onshore wind farm in Scotland, operated by Scottish Power. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningSep 2001 (completed)
  2. ConsentedJun 2002 (completed)
  3. Construction (completed)
  4. OperatingJan 2004 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
29.8 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Scottish Power
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PA22 3AE
Coordinates
56.0399, -5.1560

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Cruach Mhor compares

168th of 488largest wind farms in the UK register
100th of 199in Scotland
0.10%of listed UK wind farms capacity
β‰ˆ 68 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 29.8 MW station would generate roughly 68 GWh of electricity in a year, similar to the annual use of about 25,100 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Scottish Power

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Scottish Power Renewables
Planning authority
Argyll and Bute
Planning reference
01/01553/DET
Application submitted
18 September 2001
Permission granted
6 June 2002
Began operating
31 January 2004
Capacity in planning record
33.3 MW
Address
Cruach Mhor, Cowal, Glen Dareul, Agyll, Bute, Strathclyde
REPD reference
3585

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.