πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Slade Farm

Slade Farm is a 4.1 MW solar farm in South West England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningFeb 2013 (completed)
  2. ConsentedAug 2014 (completed)
  3. ConstructionJun 2015 (completed)
  4. OperatingNov 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.1 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
TQ7 2HE
Coordinates
50.2933, -3.7671

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Slade Farm compares

526th of 662largest solar farms in the UK register
130th of 192in South West
0.07%of listed UK solar farms capacity
β‰ˆ 3.6 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.1 MW station would generate roughly 3.6 GWh of electricity in a year, similar to the annual use of about 1,330 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Lower Slade Farm
Developer / operator
PS Renewables
Planning authority
South Hams
Planning reference
08_28/0430/13/F
Application submitted
21 February 2013
Permission granted
11 August 2014
Construction started
28 June 2015
Began operating
26 November 2015
Capacity in planning record
4.1 MW
Address
Kingsbridge, Devon, TQ7 2HE
REPD reference
2033

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.