Marley Thatch
Marley Thatch is a 6.22 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 6.22 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TQ10 9LW
- Coordinates
- 50.4248, -3.8093
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Marley Thatch compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 6.22 MW station would generate roughly 5.4 GWh of electricity in a year, similar to the annual use of about 2,020 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Octopus InvestmentsNearby generating sites
- Hatchlands Β· 5.22 MW solar farm1.7 km
- Hazard Β· 5.66 MW solar farm3.5 km
- Luson Β· 1.9 MW solar farm11.7 km
- Tope Farm Β· 3.31 MW solar farm13.5 km
- Portworthy Β· 4.02 MW solar farm14.7 km
- EP Langage Ltd Β· 905 MW CCGT gas power station14.9 km
- Slade Farm Β· 4.1 MW solar farm14.9 km
- Rydon Farm Β· 9.58 MW solar farm15.3 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Marley Thatch Solar Farm
- Developer / operator
- TGC Renewables
- Planning authority
- South Hams
- Planning reference
- 39_45/0706/12/F
- Application submitted
- 29 March 2012
- Permission granted
- 28 June 2012
- Construction started
- 28 January 2013
- Began operating
- 31 March 2013
- Capacity in planning record
- 6.3 MW
- Address
- Marley Thatch Farm, South Brent, Devon, TQ10 9LW
- REPD reference
- 1467
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026