Henley
Henley is a 5 MW solar farm in West Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- West Midlands
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- West Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SY6 6RS
- Coordinates
- 52.4877, -2.8026
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Henley compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in West Midlands All run by Greencoat CapitalNearby generating sites
- Pitchford Β· 21 MW solar farm15.5 km
- Upper Meadowley Β· 4.87 MW solar farm21.6 km
- Ironbridge B Power Station Β· 1,000 MW coal-fired power station25.8 km
- High Point Β· 3.75 MW solar farm26.9 km
- Sundorne Grove Β· 18.2 MW solar farm28.2 km
- Wrockwardine Β· 10.5 MW solar farm28.5 km
- Eaton Hill Β· 0.47 MW solar farm28.9 km
- Moor Farm Β· 3.73 MW solar farm34.3 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Henley Solar Farm
- Developer / operator
- Greencoat/ Renesola
- Planning authority
- Shropshire
- Planning reference
- 14/04930/FUL
- Application submitted
- 3 November 2014
- Permission granted
- 4 January 2016
- Construction started
- 29 December 2016
- Began operating
- 29 March 2017
- Capacity in planning record
- 6.5 MW
- Address
- Land North Of Henley Common Henley Lane Acton Scott, Shropshire, SY6 6RS
- REPD reference
- 5342
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026