Bodwen

Bodwen is a 5 MW solar farm in South West England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningMay 2013 (completed)
  2. ConsentedMar 2015 (completed)
  3. ConstructionOct 2016 (completed)
  4. OperatingFeb 2017 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
5 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PL26 8RP
Coordinates
50.4115, -4.7786

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Bodwen compares

252nd of 662largest solar farms in the UK register
72nd of 192in South West
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Bodwen Solar Park
Developer / operator
Greencoat Capital
Planning authority
Cornwall
Planning reference
PA13/03710
Application submitted
22 May 2013
Permission granted
24 March 2015
Construction started
15 October 2016
Began operating
15 February 2017
Capacity in planning record
5.5 MW
Address
Land South Of A391 Near Bodwen Bugle Cornwall, Cornwall
REPD reference
1639

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.