Transmission links · Caithness / Rattray Head / Crimond / Longside / Peterhead

Spittal–Peterhead HVDC Link

Under construction

Cable construction is underway. The approximately 203 km link includes a 166 km subsea section between Sinclair’s Bay and Rattray Head. It connects the Banniskirk and Netherton hubs and supports movement of northern Scottish generation toward demand centres.

Sources reviewed 2026-10-08 · SSEN Transmission; cable contractor NKT

Project facts

StatusUnder construction
Developer / operatorSSEN Transmission; cable contractor NKT
RegionCaithness / Rattray Head / Crimond / Longside / Peterhead
CountryScotland
Published rating2,000 MW
Rating definitionTransfer capacity
Connection / routeBanniskirk Hub ↔ Sinclair’s Bay ↔ Rattray Head near Crimond ↔ Netherton Hub near Longside
Delivery target2030 (developer target; subject to change)
Total route length203 km
Subsea section166 km

What this link contributes

This asset provides a route for electricity to move between networks or strengthens the network carrying that electricity. Its capacity cannot be added to wind, solar or power-station capacity as though it were another generator.

Banniskirk Hub ↔ Sinclair’s Bay ↔ Rattray Head near Crimond ↔ Netherton Hub near Longside

Converter stations, cable manufacture, offshore installation, landfall works and grid energisation can progress at different times. The status above describes the documented project stage rather than assuming all work packages are complete.

Milestones

  • January 2026 · Final NKT cable contracts announced
  • July 2026 · Landfall HDD works underway at Rattray Head
  • 2 October 2026 · SSEN reports Blackhills and Bower Quarry construction compounds operational
  • 2030 · Published target for link commissioning

Project location

Banniskirk, Netherton near Longside and the Rattray Head landfall area are shown separately. The Rattray circle uses the nearby lighthouse only as a geographic reference, not as the construction compound. No invented cable alignment is drawn.

Loading OpenStreetMap…

Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2’s additional outlines and route layers are explicitly identified in the developer’s map data.

Sources and review date

  1. April 2026 construction announcement
    Reviewed 2026-10-08
  2. Route and endpoints
    Reviewed 2026-10-08
  3. NKT final 525 kV cable contracts (19 January 2026)
    Reviewed 2026-10-08
  4. October 2026 construction compounds and landfall progress
    Reviewed 2026-10-08

How Octary distinguishes proposals, published ratings and live measurements

Report a correction with a source

GRID CONTEXT

Great Britain electricity now

Explore the grid →
Loading the latest published grid interval…

National figures from the Carbon Intensity API. These do not measure an individual project’s output, cable flow or data-centre electricity use.