Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· SHETGlasvaar
Glasvaar is a 36 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Craig Murrail GSP, with capacity due from October 2037. The connection agreement is held by E Power Limited.
Project stageIn planning
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2037 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-006025
- Customer
- E Power Limited
- Technology
- Wind Onshore
- Total capacity
- 36 MW
- Change in this agreement
- +36 MW
- Capacity effective from
- 31 October 2037
- Connection site
- Craig Murrail GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Other projects at Craig Murrail GSP
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem