Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· SHET

Boreland BESS

Boreland BESS is a 43 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Killin GSP, with capacity due from October 2031. The connection agreement is held by Boreland Energy Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2031 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004259
Customer
Boreland Energy Ltd
Technology
Energy Storage System
Total capacity
43 MW
Change in this agreement
+43 MW
Capacity effective from
31 October 2031
Connection site
Killin GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Killin GSP Β· Grid map

Other projects at Killin GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem