Grid infrastructure βΊ Connection queue βΊ Solar + storage
SOLAR + STORAGE Β· NGETNavenby Farm
Navenby Farm is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Coddington 400kV Substation, with capacity due from October 2034. The connection agreement is held by Coddington 10 Renewables Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2034 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004045
- Customer
- Coddington 10 Renewables Ltd
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 1.0 GW
- Change in this agreement
- +1.0 GW
- Capacity effective from
- 30 October 2034
- Connection site
- Coddington 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Other projects at Coddington 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem