πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Langage Farm

Langage Farm is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Langage 400kV Substation, with capacity due from December 2037. The connection agreement is held by Langage 10 Renewables Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Dec 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002561
Customer
Langage 10 Renewables Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
1.0 GW
Change in this agreement
+1.0 GW
Capacity effective from
19 December 2037
Connection site
Langage 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Langage Β· Grid map

Other projects at Langage 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem