Grid infrastructure › Connection queue › Wind + storage
WIND + STORAGE · SPTGreystone Knowe Windfarm
Greystone Knowe Windfarm is a 67 MW wind + storage project in planning, connecting to the SP Transmission (south Scotland) network at Gala North 132Kv Substation, with capacity due from October 2033. The connection agreement is held by Greystone Knowe Windfarm Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002370
- Customer
- Greystone Knowe Windfarm Limited
- Technology
- Demand, Energy Storage System, Wind Onshore
- Total capacity
- 67 MW
- Change in this agreement
- +67 MW
- Capacity effective from
- 31 October 2033
- Connection site
- Gala North 132Kv Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem