Grid infrastructure βΊ Connection queue βΊ Solar + storage
SOLAR + STORAGE Β· NGETFeckenham
Feckenham is a 400 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Feckenham 400kV Substation, with capacity due from October 2036. The connection agreement is held by Enso Green Holdings X Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2036 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002189
- Customer
- Enso Green Holdings X Limited
- Technology
- Demand, Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 400 MW
- Change in this agreement
- +400 MW
- Capacity effective from
- 31 October 2036
- Connection site
- Feckenham 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Feckenham 400kV Substation
- Feckenham Green Energy CentreSolar + storage Β· 1.0 GW Β· Scoping
- FeckenhamSolar + storage Β· 500 MW Β· Scoping
- Feckenham Energy ParkBattery storage Β· 500 MW Β· Scoping
- Boom Power Feckenham Generation HubSolar + storage Β· 400 MW Β· Scoping
- Feckenham PV & BESS StationSolar + storage Β· 400 MW Β· Scoping
- Feckenham Greener Grid ParkBattery storage Β· 150 MW Β· Scoping
- Feckenham Greener Grid ParkBattery storage Β· 12 MW Β· Scoping
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem