Grid infrastructure › Connection queue › Offshore wind
OFFSHORE WIND · SHETBowdun (ex Cluaran Deas Ear) Offshore Wind Farm
Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm is a 1.0 GW offshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Hurlie 400kV substation, with capacity due from December 2035. The connection agreement is held by Bowdun Offshore Wind Farm Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Dec 2035 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002091
- Customer
- Bowdun Offshore Wind Farm Limited
- Technology
- Wind Offshore
- Total capacity
- 1.0 GW
- Change in this agreement
- +1.0 GW
- Capacity effective from
- 31 December 2035
- Connection site
- Hurlie 400kV substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
Connection site
The connection site could not be placed on the map.
Other projects at Hurlie 400kV substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem