Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· NGETBryn Rhudd Energy Park
Bryn Rhudd Energy Park is a 159 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Pont Abraham GSP, with capacity due from October 2028. The connection agreement is held by Bryn Rhudd Energy Park Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2028 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001918
- Customer
- Bryn Rhudd Energy Park Limited
- Technology
- Wind Onshore
- Total capacity
- 159 MW
- Change in this agreement
- +159 MW
- Capacity effective from
- 31 October 2028
- Connection site
- Pont Abraham GSP
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Other projects at Pont Abraham GSP
- BrynGwyn Energy ParkOnshore wind Β· 250 MW Β· Scoping
- Lan Fawr Energy ParkOnshore wind Β· 246 MW Β· Scoping
- Garreg Fawr Energy ParkOnshore wind Β· 190 MW Β· Scoping
- BlaenCothi Energy ParkOnshore wind Β· 145 MW Β· Scoping
- Builth WellsOnshore wind Β· 133 MW Β· Scoping
- Nant Ceiment Energy ParkOnshore wind Β· 88 MW Β· Scoping
- Bryn Gilwern Energy ParkOnshore wind Β· 75 MW Β· Scoping
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem