Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SHET

Keith 132 Greener Grid Park

Keith 132 Greener Grid Park is a 48 MW battery storage project under construction or commissioning, connecting to the SSEN Transmission (north Scotland) network at Keith 132kV Substation, with capacity due from April 2029. The connection agreement is held by Keith Storage Solutions Limited.

Project stageUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingFrom Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001129-2
Customer
Keith Storage Solutions Limited
Technology
Energy Storage System, Reactive Compensation
Total capacity
48 MW
Change in this agreement
+48 MW
Capacity effective from
1 April 2029
Connection site
Keith 132kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Under Construction/Commissioning
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Keith · Grid map

Other projects at Keith 132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem