Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Fleet EGH (Tertiary)

Fleet EGH (Tertiary) is a 48 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Fleet 400kV Substation, with capacity due from January 2027. The connection agreement is held by Fleet Green Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000544
Customer
Fleet Green Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
48 MW
Change in this agreement
+48 MW
Capacity effective from
13 January 2027
Connection site
Fleet 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Fleet Β· Grid map

Other projects at Fleet 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem