🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Bramley (tertiary)

Bramley (tertiary) is a 57 MW solar + storage project under construction or commissioning, connecting to the National Grid (England & Wales) network at Bramley 400kV Substation, with capacity due from October 2027. The connection agreement is held by Bramley Solar Limited.

Project stageUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingFrom Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000396
Customer
Bramley Solar Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
30 October 2027
Connection site
Bramley 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Under Construction/Commissioning
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bramley · Grid map

Other projects at Bramley 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem