South Humber Bank

South Humber Bank is a 1.4 GW gas project built and connected, connecting to the National Grid (England & Wales) network at South Humber Bank 400kV Substation. The connection agreement is held by EP UK Power Development II Ltd.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2039 (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000366
Customer
EP UK Power Development II Ltd
Technology
CCGT (Combined Cycle Gas Turbine)
Total capacity
1.4 GW
Already connected
1.4 GW
Change in this agreement
+35 MW
Capacity effective from
30 October 2039
Connection site
South Humber Bank 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near South Humber Bank · Grid map

Other projects at South Humber Bank 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem