Hartlepool is a 1.2 GW nuclear project built and connected, connecting to the National Grid (England & Wales) network at Hartlepool 275kV Substation. The connection agreement is held by EDF Energy Nuclear Generation Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000139
Customer
EDF Energy Nuclear Generation Limited
Technology
Nuclear
Total capacity
1.2 GW
Already connected
1.2 GW
Connection site
Hartlepool 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Hartlepool Β· Grid map