πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Power plants β€Ί Gas power plants β€Ί Tennessee

OCTARY USA Β· GAS POWER PLANTS

Gas power plants in Tennessee

Natural gas power plants in the United States: combined cycle, combustion turbines, engines and steam units. Click a state to drill down, or search near a place.

Operating14plants
Operating capacity7,383 MWnameplate
Under construction778 MW1 plants
Whole pipeline3,386 MWplanned, approved and building

Map

Loading plants…
OperatingUnder constructionApprovedPlannedRetiredCancelled

Plants

16 plants
PlantCapacityStageStateOwner / operatorYear
Kingston 1,831 MW In planning TN
Roane
Tennessee Valley Authority 2027
Johnsonville 1,676 MW Operating TN
Humphreys
Tennessee Valley Authority 1975
Lagoon Creek 1,625 MW Operating TN
Haywood
Tennessee Valley Authority 2001
Cumberland (TN) 1,556 MW Under construction TN
Stewart
Tennessee Valley Authority 2034
Allen 1,171 MW Operating TN
Shelby
Tennessee Valley Authority 2018
John Sevier 997 MW Operating TN
Hawkins
Tennessee Valley Authority 2012
Gallatin (TN) 663 MW Operating TN
Sumner
Tennessee Valley Authority 1975
Gleason Generating Facility 568 MW Operating TN
Weakley
Tennessee Valley Authority 2000
Brownsville Peaking Power 460 MW Operating TN
Haywood
Tennessee Valley Authority 1999
Tennessee Eastman Operations 83.8 MW Operating TN
Sullivan
Eastman Chemical Co-TN Ops 1966
Primient Loudon Plant 61.4 MW Operating TN
Loudon
PRIMIENT, LLC 2016
Domtar Kingsport Mill 50.0 MW Operating TN
Sullivan
Domtar Paper Co LLC Kingsport Mill 2006
Vanderbilt University Power Plant 13.5 MW Operating TN
Davidson
Vanderbilt University 2015
MTSU Power Co-Gen Plant 5.0 MW Operating TN
Rutherford
Middle Tennessee State University 1997
University of Tennessee Steam Plant 5.0 MW Operating TN
Knox
University of Tennessee 1996
Opryland USA 4.5 MW Operating TN
Davidson
Gaylord Entertainment Co 1995

Source: U.S. Energy Information Administration, Form EIA-860M, Monthly Update to the Annual Electric Generator Report, September 2026. Includes generators of 1 MW and over at plants connected to the grid. Planned dates are developers' targets reported to EIA and often move. US EV charging map