Kingston

Kingston is a 3,531 MW operating power plant in Roane County, Tennessee, operated by Tennessee Valley Authority.

Plant statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingFeb 1954 (current stage)
  5. Closed (not yet reached)

Planned retirement: Dec 2027. This plant has generators at more than one stage; see the table below.

Open in Google MapsMore gas power plants in Tennessee

Generators

Each generating unit EIA lists at this plant.

UnitTechnologyCapacityStatusOnlineRetired / planned retirement
5Conventional Steam Coal200 MW OperatingJan 1955Planned Dec 2027
6Conventional Steam Coal200 MW OperatingMar 1955Planned Dec 2027
7Conventional Steam Coal200 MW OperatingMay 1955Planned Dec 2034
8Conventional Steam Coal200 MW OperatingAug 1955Planned Dec 2034
9Conventional Steam Coal200 MW OperatingDec 1955Planned Dec 2034
1Conventional Steam Coal175 MW OperatingFeb 1954Planned Dec 2027
2Conventional Steam Coal175 MW OperatingApr 1954Planned Dec 2027
3Conventional Steam Coal175 MW OperatingJun 1954Planned Dec 2027
4Conventional Steam Coal175 MW OperatingJul 1954Planned Dec 2027
CTG1Natural Gas Fired Combined Cycle455 MW Planned, approvals not yet soughtTarget Dec 2027
STG1Natural Gas Fired Combined Cycle323 MW Planned, approvals not yet soughtTarget Dec 2027
G1Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G2Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G3Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G4Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G5Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G6Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G7Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G8Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G9Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G10Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G11Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G12Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G13Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G14Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G15Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027
G16Natural Gas Fired Combustion Turbine66 MW Planned, approvals not yet soughtTarget Dec 2027

Plant details

Operator
Tennessee Valley Authority
Location
Roane County, Tennessee
Balancing authority
TVA
Sector
Electric Utility
Capacity
Operating: 1,700 MW
Planned: 1,831 MW
First unit online
Feb 1954
EIA plant ID
3407

Location

35.8992, -84.5194

Nearby power plants

Source: U.S. Energy Information Administration, Form EIA-860M, September 2026. Planned dates are targets reported by the developer and often change. Report a problem