United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Bobcat Energy Storage

Bobcat Energy Storage is a 75.0 MW battery storage request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1780
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Antelope Substation 66kV
Location
Los Angeles County, California
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
July 2022
Withdrawn
March 2021

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem