Fortistar VAN

Fortistar VAN is a 79.9 MW gas request withdrawn in the NYISO interconnection queue, in Richmond County, New York, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2001 (completed)
  2. Withdrawn / abandonedMay 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
91
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
Fortistar, LLC
Connection point (POI)
Goethals/Fresh Kills 138kV
Location
Richmond County, New York
Technology
Gas: 79.9 MW
Total requested
79.9 MW
Queue status
Withdrawn
Entered queue
20 March 2001
Withdrawn
May 2009

Location

Marker shows the centre of Richmond County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Richmond County