United States › Grid › Interconnection queues › Illinois
GAS · PJMInvenergy Nelson Expansion LLC
Invenergy Nelson Expansion LLC is a 190 MW gas request built and operating in the PJM interconnection queue, in Lee County, Illinois, connecting to ComEd.
Request details
- Queue ID
- AA2-030
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Nelson
- Location
- Lee County, Illinois
- Technology
- Gas: 190 MW
- Total requested
- 190 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 24 December 2014
- Proposed online date
- May 2023
- Came online
- May 2023
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Shady Oaks Wind Power ProjectOnshore wind · 106 MW · agreement signed
- Steward Creek SolarSolar · 300 MW · in study
- South Dixon SolarSolar · 300 MW · in study
- Solar project AH1-151, Lee CountySolar · 200 MW · in study
- Solar project AH1-150, Lee CountySolar · 200 MW · in study
- Steward Creek SolarSolar · 200 MW · in study
- South Dixon SolarSolar · 200 MW · in study
- Solar project AH1-044, Lee CountySolar · 200 MW · in study
- Solar project AH1-338, Lee CountySolar · 180 MW · in study
- Battery storage project AH2-015, Lee CountyBattery storage · 110 MW · in study
- Steward Creek SolarSolar · 100 MW · in study
- Battery storage project AH2-123, Lee CountyBattery storage · 100 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem