Solar project AG2-296, Crawford County

Solar project AG2-296, Crawford County is a 30.0 MW solar request withdrawn in the PJM interconnection queue, in Crawford County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-296
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
South Berwick - Galion 345 kV
Location
Crawford County, Ohio
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
23 March 2021
Proposed online date
December 2024
Withdrawn
December 2024

Location

Marker shows the centre of Crawford County; the queue data does not give exact sites.