Onshore wind project GEN-2013-014, Webster County

Onshore wind project GEN-2013-014, Webster County is a 25.5 MW onshore wind request withdrawn in the SPP interconnection queue, in Webster County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandonedApr 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2015 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2013-014
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Tap Guide Rock - Pauline (GEN-2008-123N Tap) 115kV
Location
Webster County, Nebraska
Technology
Wind: 25.5 MW
Total requested
25.5 MW
Service type
NRIS and ERIS
Study phase
TERMINATED
Queue status
Withdrawn
Entered queue
29 March 2013
Proposed online date
December 2015
Came online
December 2015
Withdrawn
April 2016

Location

Marker shows the centre of Webster County; the queue data does not give exact sites.