🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

GAS · NYISO

Island Park Energy Center CCPP

Island Park Energy Center CCPP is a 295 MW gas request withdrawn in the NYISO interconnection queue, in Nassau County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2014 (completed)
  2. Withdrawn / abandonedFeb 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
427
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Island Park Energy Center, LLC
Connection point (POI)
Barrett Power Station 138kV
Location
Nassau County, New York
Technology
Gas: 295 MW
Total requested
295 MW
Queue status
Withdrawn
Entered queue
24 January 2014
Withdrawn
February 2017

Location

Marker shows the centre of Nassau County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Nassau County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem