πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OTHER Β· WEST

Other project Q95, Los Angeles County

Other project Q95, Los Angeles County is a 346 MW other request withdrawn in the West interconnection queue, in Los Angeles County, California, connecting to Los Angeles Department of Water and Power.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q95
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Scattergood 230kV Switchyard
Location
Los Angeles County, California
Technology
Hydrogen: 346 MW
Total requested
346 MW
Queue status
Withdrawn
Entered queue
19 January 2023
Proposed online date
January 2030
Withdrawn
October 2025

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem