United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

COAL Β· MISO

Coal project G364, Manistee County

Coal project G364, Manistee County is a 425 MW coal request withdrawn in the MISO interconnection queue, in Manistee County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2003 (completed)
  2. Withdrawn / abandonedAug 2004 (project stopped here)
  3. ConsentedAug 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G364
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Manistee County, Michigan
Technology
Coal: 425 MW
Total requested
425 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
10 October 2003
Agreement signed
25 August 2004
Proposed online date
May 2007
Withdrawn
August 2004

Location

Marker shows the centre of Manistee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Manistee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem