ONSHORE WIND Β· MISO

Onshore wind project J194, Manistee County

Onshore wind project J194, Manistee County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Manistee County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2011 (completed)
  2. Withdrawn / abandonedAug 2011 (project stopped here)
  3. ConsentedAug 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J194
Grid region
MISO (Midcontinent)
Connection point (POI)
Keystone - Ludington 345kV
Location
Manistee County, Michigan
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
4 February 2011
Agreement signed
3 August 2011
Proposed online date
September 2012
Withdrawn
August 2011

Location

Marker shows the centre of Manistee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Manistee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem